2009-2010 Theatre Production Calendar

View production tasks

Production Tasks Prior to Opening

"Fiddler on the Roof"

"Sight Unseen"
"Twelth Night"
"The Resistible Rise of Arturo Ui"
Director's Written Concept Statement 18 weeks June 10 July 8 Sept 10 Nov 5
Budget/Production Outlined 18 weeks June 10 July 8 Sept 10 Nov 5
Preliminary Set and Costume Designs 16 weeks June 24 July 22 Sept 24 Nov 19
Preliminary Prop List 15 weeks July 1 July 29 Oct 1 Nov 26
Scenic Estimate 15 weeks July 1 July 29 Oct 1 Nov 26
Costume Estimate 15 weeks July 1 July 29 Oct 1 Nov 26
Revised Set and Costume Designed 14 weeks  July 8  Aug 5 Oct 8  Dec 3
Final Set Design 12 weeks July 22 Aug 19 Oct 22 Jan 14
Final Costume Design 10 weeks  Aug 5 Sept 2 Nov 5 Jan 28
Set Design Drawings 10 weeks Aug 5 Sept 2 Nov 5 Jan 28
Set Construction Drawings 8 weeks Aug 19 Sept 16 Nov 19 Feb 11
Costume Construction Begins 8 weeks Aug 19 Sept 16 Nov 19 Feb 11
Set Construction Begins 7 weeks Aug 26 Sept 23 Nov 26 Feb 18
Preliminary Sound Cue List 6 weeks Sept 2 Sept 30 Dec 3 Feb 25
Preliminary Prop Viewing 5 weeks Sept 9 Oct 7 Dec 10 Mar 4
Preliminary Light Design 4 weeks Sept 16 Oct 14 Jan 14 Mar 11
Final Prop List 3 weeks Sept 23 Oct 21 Jan 21 Mar 25
Final Light Design 3 weeks Sept 23 Oct 21 Jan 21 Mar 25
Final Sound Plot 3 weeks Sept 23 Oct 21 Jan 21 Mar 25
Final Prop Viewing 2 weeks Sept 30 Oct 28 Jan 28 Apr 1
Light Hang 2 weeks Sept 30 Oct 28 Jan 28 Apr 1
Costume Parade 9 days Oct 6 Nov 3 Feb 2 Apr 6
Dry Tech 6 days Oct 9 Nov 6 Feb 5 Apr 9
Cue to Cue Tech 5 days Oct 10 Nov 7 Feb 6 Apr 10
First Dress 4 days Oct 11 Nov 8 Feb 7 Apr 11
Second Dress 3 days Oct 12 Nov 9 Feb 8 Apr 12
Third Dress 2 days Oct 13 Nov 10 Feb 9 Apr 13
Fourth Dress 1 day Oct 14 Nov 11 Feb 10 Apr 14
Opening 0 days Oct 15 Nov 12 Feb 11 Apr 15
Strike   Oct 24 Nov 21  Feb 20 Apr 24